Successful Completion of PE315 Hot Tapping Project for TTCL Gas Pipeline

The PE315 hot tapping and branch connection project for TTCL  has been successfully completed, further strengthening the reliability and flexibility of the local natural gas distribution network.

The project involved a PE315 pipeline with a design pressure of 0.8 MPa and an operating pressure of 0.35 MPa, with natural gas as the transmission medium. By adopting advanced hot tapping technology, the project team successfully connected a DN200 branch line to the existing pipeline without interrupting gas supply, ensuring continuous operation throughout the construction process.

Through the implementation of the hot tapping process, the pipeline connection was carried out under live conditions, eliminating the need for shutdown or service disruption. This approach significantly improved construction efficiency while minimizing the impact on downstream users.

During the execution, strict adherence to safety standards and technical procedures was maintained. Considering the characteristics of natural gas, comprehensive safety measures and real-time monitoring were applied to ensure a fully controlled hot tapping operation. The project achieved zero accidents and zero leakage, demonstrating a high level of operational excellence.

The successful completion of this PE315 hot tapping project highlights the effectiveness of hot tapping solutions in polyethylene (PE) pipeline systems and showcases the capability to safely perform live pipeline modifications under medium-pressure conditions.

This project provides a solid reference for future hot tapping applications in gas distribution networks and supports the continued advancement of safe, efficient, and uninterrupted energy supply infrastructure.

f4f1a096e1a16ba90717cc31071b5b0
f4f1a096e1a16ba90717cc31071b5b0
d172184f9357beb3b79196e8e53f5f2
d172184f9357beb3b79196e8e53f5f2
d4fc3a42925b3743625f36ada2a2ff7
d4fc3a42925b3743625f36ada2a2ff7
d2a4785c52c7ee02c93393dfb4b5233
d2a4785c52c7ee02c93393dfb4b5233
c7190c061031e3fd9b3af2da1f16c45
c7190c061031e3fd9b3af2da1f16c45
acbeb016e76618521c8e4cfa6a7f147
acbeb016e76618521c8e4cfa6a7f147
prev
Successful Completion of DN300 Hot Tapping Project for Xinjiang Gas Ensures Safe and Stable Natural Gas Supply
recommended for you
no data
Get in touch with us

Taitat Changlin Pipeline Technology (Jiangxi) Co., Ltd.

For over 40 years, we have provided safe, efficient and proven solutions for pressure pipeline systems around the world, ensuring the safe flow of energy.
Contact with us
WhatsApp: +86 13570819716
Add: NO.1208 Saiwei Avenue, EDZ, Xinyu City Jiangxi Province, China.


Copyright © 2026 Taitat Changlin | Sitemap  |  Privacy Policy
Customer service
detect